Construction Updates

 

South Medford Support Services 

Construction is progressing well. The North Wing Building steel framing is complete with siding starting in mid-November. The exterior stud framing and steel entry for the South Wing Building is underway.

 

con 1                   con 2 

 

 

West Medford Branch

The exterior brick veneer is complete with aluminum panels scheduled to be installed by the end of this month. Interior painting, windows, flooring and ceiling tile is complete. Exterior work on walkways and parking has also started with anticipated completion by mid-November. 

 con 3            con 4